Hemisphere Freight UK Delivers 180MT Super Grid Power Transformer

PPG UK member, Hemisphere Freight Services (HFS), were tasked with finding the most cost-effective and workable solution to deliver a 132kv Super Grid power transformer, weighing 180 tonnes. Following discharge from an ocean vessel, which originated in Korea, Hemisphere took responsibility of safely transporting the transformer from Rotterdam Port through to the National Grid site on the UK’s east coast.

 

After several route surveys by HFS’s project managers and trucking company, it was decided that the only possible route would be to discharge the cargo at the Port of Lowestoft. The Port of Lowestoft is heavily restricted for project cargo operations, due to local bridge restrictions to the north quay and shallow draft, as well as quayside heavy-lift restrictions to the south quay.

 

HFS project managers therefore decided to charter a specialist sea-going barge with a shallow draft and hydraulic roll-on/roll-off ramps. This method was chosen so that once the transformer was loaded onto specifically engineered and positioned stands in Rotterdam, it would be possible to roll onto the barge using 10 x SPMT hydraulic axles to lift and roll the cargo off the barge at the discharge port.

 

Due to the road weight, height and width restrictions, the transformer was built into a unique ‘Girder Bridge’ trailer supported by 20 modular axles and 2 x push/pull tractor units. This adhered to special permits issued by the Highways Authority to allow the safe delivery of the transformer. Moving in convoy with a police escort at a maximum of 12.5mph, the route of approximately 27 miles took almost 7 hours to complete on a Saturday.

 

On Sunday, HFS specialist installation contractor began to place precise jacking and skidding gear under the transformer to manoeuvre it into a specific final position required by the end user, a process which took a further 3 days to complete.

 

In addition to the main transformer unit, HFS also had to undertake full customs clearance procedures in the Netherlands and handle an additional 42 cases of accessory parts in Rotterdam, which were to be installed around the main transformer. These cases of parts had to be delivered to the wind farm site in a specific order.

 

To comply with site requirements, HFS arranged to unload the cases from containers in Rotterdam and truck them to our 110,000ft2 warehouse in Ipswich, Suffolk, where they stored the cases until called for delivery by the installation engineers - finally delivering to site using our fleet of curtain sided trailers.

 

 

Throughout the entire planning, execution, port operations, delivery and installation, Hemisphere project managers followed the cargo every step of the journey to ensure a smooth and seamless delivery.